Tuesday 2 December 2014

What is your answer

What is your answer

The Product Owner on a project, on which you are the Scrum Master, has identified disaster situations, such as earthquakes and tsunamis, as potential risks to the underwater transnational communication sea link. The Stakeholders have suggested that steps to safeguard the foundations of the ocean infrastructure be taken at the earliest, and also have recommended that a contingency reserve be created, which could be used in case of disaster situations. This is an example of:

a) Risk Mitigation.
b) Risk Prioritization.
c) Risk Avoidance.
d) Risk Assessment.

No comments:

Post a Comment